Monday, December 15, 2014

MEDFORD ADDITION - DAY 6

View from the mountain (of dirt)

Work on the primary foundation is mostly complete.   Masons are busy today parging foundation and applying a tar coating on the portions of the wall that will be buried.    One glitch is that the Township building inspector is requiring a soil compaction test on the mountain of dirt I am standing on.  This involves laboratory testing of soil and then compaction of soil, if useable, under the supervision and constant testing of an engineer.    This will likely delay the project a few days while all the details of this requirement are coordinated.


We were able to start excavating for the mudroom/side entry foundation.  Obviously we would have liked to have done this in conjunction with the main foundation, however, it's location right adjacent to the driveway was a concern so we elected to do this separate, once the primary foundation was complete.